Case Studies

  • Full site clearance across a 3 acre site
  • Access roads and site preparation
  • Strip out to shell and core
  • Asbestos removal
  • Demolition of a 6 storey building
  • Demolition of multiple structures
  • Ground remediation and basement works
  • On site crushing and reuse of materials
  • Dual contract at The Crescent and Atlas House, City of London
  • 11 week programme in a live urban environment
  • Full internal strip out to shell and core
  • Removal of existing MEP plant
  • Asbestos removal works
  • Temporary site services and alarms installed
  • Hoarding, power supplies and CCTV installed
  • Materials removed and stored for reuse
  • Localised demolition works
  • New service riser formation
  • Roof demolition works
  • Bespoke temporary structural support
  • Below ground drainage installation
  • New structural steel for openings
  • Structural steel for roof extension
  • Concrete and masonry remedial works
  • New skate park construction with drainage and attenuation
  • Themed playground with specialist equipment
  • Below ground attenuation and French drains
  • Resin surfacing and hardstanding areas
  • Toilet and catering facilities installed
  • CCTV infrastructure and utility connections
  • Landscaping with permeable paths and planting
  • New route to the Covid memorial peace garden
  • Dual enabling works contract for international hotel group
  • Complete strip out back to shell & core (listed building)
  • 10 week programme with 60+ operatives mobilised
  • Installation of temporary services, fire & intruder alarms
  • Full R&D asbestos survey & licensed removal
  • MEP plant drain down & removal works
  • Heritage protection & internal hoarding installations
  • 5,000 raised access floor tiles removed & rehomed (200+ pallets)
  • Enabling works including soft strip & partial demolition
  • Demolition of 1,500m² slab & hard standings
  • Formation of pad foundations, ground beams & external slabs
  • Construction of lift pit, ramps, stairs & French drainage system
  • Base works for 55t structural steel gantry (design & install)
  • Architectural staircases, handrails & galvanised mesh flooring
  • New cantilevered slab, drainage & structural steel extension
  • Excavation & installation of new service trenches under RF controls
  • Full internal strip out back to existing structure
  • Removal of ceilings, walls & floor finishes
  • Validation & isolation of existing services
  • Works delivered within live, occupied demise
  • Close coordination with neighbouring contractors
  • Emergency services maintained throughout programme
  • Site specific logistics strategy with GF hoarding installation
  • Modified split shifts for controlled waste movements
  • Internal strip out of existing M&E plant across entire demise
  • Controlled demolition of AHUs, pumps & AC equipment
  • Removal of associated ductwork from roof to basement (9 floors)
  • External scaffold & hoist logistics to restricted pit lane access
  • Internal material distribution via goods lift & gantries
  • Out-of-hours working to protect neighbouring occupiers
  • On-site fabrication & installation of GRP to risers
  • Full internal strip out back to shell & core
  • Removal of partitions, doors, linings, ceilings & floor finishes
  • Decommissioning & removal of all services, including lifts
  • Careful hand removal of paint to retain exposed brickwork
  • MEPH validation & isolation of existing services
  • Coordinated asbestos removal & ASB5 notification for AIB
  • Basement trial pits, window samples & opening-up investigations
  • Early structural budgeting, sequencing & programme support